REMAGHIC – Two years Running

REMAGHIC – Two years Running

Last September in San Sebastian, the Remaghic Project partners held the 24 month meeting general assembly. During the last months many decisions have been taken on the best chain of processes to recycle rare earths and on the design of the currently manufactured...
WP4 – Validation of the New Recycling Plant

WP4 – Validation of the New Recycling Plant

The performance of the Mg Recycling Test Unit has been verified by performing different tests, checking movements, automation, melting and heating system, correct scrap charge and ingots discharge. Its validation will be completed by realizing melting tests in...
WP1 – Recovery Demonstrator

WP1 – Recovery Demonstrator

WP1 partners are working in order to describe the technical feasibility of the selected route (La and Ce recovery from NiMH batteries) at a higher TRL and its economic and environmental assessment (task 1.4). A detailed evaluation of the different steps involved in...
WP5 – Life-Cycle Analysis (II)

WP5 – Life-Cycle Analysis (II)

CIDAUT and Grupo Antolín have analyzed, through LCA models, the environmental impact of different technical options for the Remaghic Mg recovery system under development, in order to define the pilot plant where validate the developed process. The higher amount of...

WP5 – Life-Cycle Analysis (I)

Fraunhofer Institute ICT, in the framework of the Remaghic project, successfully obtained results for the environmental and economic criterion for 6 REE Recycling Process routes. Life Cycle Assessment studies have been performed, following the international standards...